Power Usage Service

Energy and cost-efficient power supply

We are committed to sustainability. With a PUE of 1.3, our FRA01 data center is considerably more efficient than other data centers. Our aim is to minimize costs and conserve resources in data center operation. Your advantage is maximum power supply transparency. With us, you only pay for the power that you actually use. Current and historical usage data, as well as power quality (frequency, voltage) is available on our online service portal at all times.

maincubes serviceportal
  • Power usage servicePower usage service
  • measurement of power usage per rackmeasurement of power usage per rack
  • monthly billing of power usage taking into account the electricity price (maincubes power purchase price “EK”), the PUE and a handling fee of 2%monthly billing of power usage taking into account the electricity price (maincubes power purchase price “EK”), the PUE and a handling fee of 2%
  • guaranteed PUE of 1.3 (FRA01) or 1.6 (AMS01) from 60% use of capacityguaranteed PUE of 1.3 (FRA01) or 1.6 (AMS01) from 60% use of capacity
  • billing formula for the monthly service fee for electricity consumption: EK electricity * PUE * Consumption in kWh + EK electricity * Consumption in kWh * Handling feebilling formula for the monthly service fee for electricity consumption: EK electricity * PUE * Consumption in kWh + EK electricity * Consumption in kWh * Handling fee
  • option for mainsuite in FRA01: Lower, individual PUE based on a higher temperature set point in the cold aisleoption for mainsuite in FRA01: Lower, individual PUE based on a higher temperature set point in the cold aisle
  • option for green power with certificate (on request)option for green power with certificate (on request)
  • mainpower

  • Power usage service
  • measurement of power usage per rack
  • monthly billing of power usage taking into account the electricity price (maincubes power purchase price “EK”), the PUE and a handling fee of 2%
  • guaranteed PUE of 1.3 (FRA01) or 1.6 (AMS01) from 60% use of capacity
  • billing formula for the monthly service fee for electricity consumption: EK electricity * PUE * Consumption in kWh + EK electricity * Consumption in kWh * Handling fee
  • option for mainsuite in FRA01: Lower, individual PUE based on a higher temperature set point in the cold aisle
  • option for green power with certificate (on request)